Mud Dredging in Ciliwung River Accelerated
access_time March 14 2023 02:02 PM remove_red_eye 1016
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
Central Jakarta Water Resources (SDA) Sub-agency keeps speeding up dredging mud in the Ciliwung River segment of Jalan Kramat Kwitang, Senen.
It is targeted to be completed on June 9, 2024
The dredging that conducts in June 2022 has now reached 28.21 percent.
Central Jakarta SDA Sub-agency Head, Mustajab expressed dredging mud in the Ciliwung River segment of Jalan Kramat Kwitang is aimed to reduce inundation and flooding in the surrounding area.
4,168 Cubic Meters of Mud Collected from Melati Reservoir"It is targeted to be completed on June 9, 2024," he said, Tuesday (3/14).
Until February 14, it has been 228 meters long, or 28.21 percent of the total 808 meters long.
"The river has 24 meters wide," he explained.
This work involved ten personnel plus one amphibious excavator and two trucks.
"Hopefully, it is capable of maximizing water volume and reducing inundation in Senen," he stated.